G00010MWEN: TYSELEY WASTE DISPOSAL SITE

Return to Table

GeneralMapSummaryLFMWh
RO Period Capacity (kW) Load Factor MWh ROCs
2002/2003 28,000 50.5% 123,758 0
2003/2004 32,600 49.6% 131,138 0
2004/2005 28,000 46.4% 113,859 0
2005/2006 32,600 67.2% 191,980 0
2006/2007 32,600 53.2% 142,465 0
2007/2008 32,600 65.5% 187,471 0
2008/2009 32,600 33.0% 94,364 0
2009/2010 32,600 35.0% 99,888 0
2010/2011 32,600 33.3% 95,220 0
2011/2012 32,600 36.2% 103,726 0
2012/2013 32,600 32.4% 92,404 0
2013/2014 32,600 37.3% 106,531 0
2014/2015 32,600 31.5% 89,852 0
2015/2016 (11) 32,600 24.7% * 64,714 0
2016/2017 (1) 32,600 38.9% * 9,141 0
Annual Totals to end Apr-16 72,7530
Rolling Load Factor42.3 %
Annual Load Factor to end Apr-1625.4 %

Notes:

1. RO period is the 12 months from 1 April to 31 March
2. Capacity is the total installed generating capacity in kW
3. Load Factor is calcuated for the 12 months of the RO period.
4. An asterisk (*) denotes fewer than 12 months of data is available in a given period; the actual number of months of data is in brackets in the first column.
5. The number of ROCs per MWh depends on whether the generator is subsidised under the RO and, from April 2009, the band into which the generator and technology falls.