RO Period Capacity (kW) Load Factor MWh ROCs
2004/2005 45,000 44.3% 174,662 0
2005/2006 45,000 37.7% 148,578 0
2006/2007 45,000 51.0% 201,132 0
2007/2008 45,000 43.9% 173,478 0
2008/2009 45,000 41.4% 163,185 0
2009/2010 45,000 42.0% 165,694 0
2010/2011 (10) 45,000 27.9% * 91,680 0
2011/2012 45,000 56.3% 222,469 0
2012/2013 45,000 35.0% 137,841 0
2013/2014 45,000 48.5% 191,205 0
2014/2015 45,000 47.9% 188,815 0
2015/2016 45,000 56.6% 223,834 0
2016/2017 45,000 29.6% 116,822 0
2017/2018 (8) 45,000 33.6% * 88,521 0
Annual Totals to end Nov-17 153,2880
Rolling Load Factor42.4 %
Annual Load Factor to end Nov-1738.9 %

Notes:

1. RO period is the 12 months from 1 April to 31 March
2. Capacity is the total installed generating capacity in kW
3. Load Factor is calcuated for the 12 months of the RO period.
4. An asterisk (*) denotes fewer than 12 months of data is available in a given period; the actual number of months of data is in brackets in the first column.
5. The number of ROCs per MWh depends on whether the generator is subsidised under the RO and, from April 2009, the band into which the generator and technology falls.