G00482HYSC: Clunie Power Station

Return to Table

GeneralMapSummaryLFMWh
RO Period Capacity (kW) Load Factor MWh ROCs
2004/2005 61,200 41.1% 220,135 0
2005/2006 61,200 35.9% 192,579 0
2006/2007 61,200 43.6% 233,846 0
2007/2008 61,200 39.8% 213,793 0
2008/2009 61,200 40.8% 218,810 0
2009/2010 61,200 32.0% 171,816 0
2010/2011 61,200 30.9% 165,877 0
2011/2012 61,200 46.8% 251,788 0
2012/2013 61,200 30.8% 164,867 0
2013/2014 61,200 42.2% 226,290 0
2014/2015 61,200 38.2% 204,545 0
2015/2016 61,200 41.9% 225,319 0
2016/2017 (7) 61,200 22.0% * 69,202 0
Annual Totals to end Oct-16 207,5100
Rolling Load Factor38.1 %
Annual Load Factor to end Oct-1638.6 %

Notes:

1. RO period is the 12 months from 1 April to 31 March
2. Capacity is the total installed generating capacity in kW
3. Load Factor is calcuated for the 12 months of the RO period.
4. An asterisk (*) denotes fewer than 12 months of data is available in a given period; the actual number of months of data is in brackets in the first column.
5. The number of ROCs per MWh depends on whether the generator is subsidised under the RO and, from April 2009, the band into which the generator and technology falls.