G01027HYSC: Foyers Natural Run Off

Return to Table

GeneralMapSummaryLFMWh
RO Period Capacity (kW) Load Factor MWh ROCs
2006/2007 300,000 4.4% 114,600 0
2007/2008 300,000 0.0% 661 0
2008/2009 (10) 300,000 13.1% * 286,383 0
2009/2010 300,000 15.0% 395,496 0
2010/2011 (10) 300,000 3.4% * 75,430 0
2011/2012 300,000 4.0% 104,263 0
2012/2013 (11) 300,000 2.5% * 60,101 0
2013/2014 (11) 300,000 3.9% * 93,859 0
2014/2015 300,000 4.2% 110,595 0
2015/2016 (8) 300,000 3.3% * 57,991 0
2016/2017 (2) 300,000 0.1% * 260 0
Annual Totals to end Sep-16 50,1750
Rolling Load Factor4.9 %
Annual Load Factor to end Sep-161.9 %

Notes:

1. RO period is the 12 months from 1 April to 31 March
2. Capacity is the total installed generating capacity in kW
3. Load Factor is calcuated for the 12 months of the RO period.
4. An asterisk (*) denotes fewer than 12 months of data is available in a given period; the actual number of months of data is in brackets in the first column.
5. The number of ROCs per MWh depends on whether the generator is subsidised under the RO and, from April 2009, the band into which the generator and technology falls.