R00007RPWA G00426FWWA : Gwynt y Mor

Return to Table

GeneralMapSummaryLFMWh
RO Period Capacity (kW) Load Factor MWh ROCs
2013/2014 (7) 576,000 1.6% * 47,180 0
2014/2015 576,000 13.9% 702,428 1,323,890
2015/2016 576,000 32.3% 1,633,600 3,267,200
2016/2017 (7) 576,000 26.1% * 773,576 1,302,720
Annual Totals to end Oct-16 1,688,3303,132,230
Rolling Load Factor22.3 %
Annual Load Factor to end Oct-1633.4 %

Notes:

1. RO period is the 12 months from 1 April to 31 March
2. Capacity is the total installed generating capacity in kW
3. Load Factor is calcuated for the 12 months of the RO period.
4. An asterisk (*) denotes fewer than 12 months of data is available in a given period; the actual number of months of data is in brackets in the first column.
5. The number of ROCs per MWh depends on whether the generator is subsidised under the RO and, from April 2009, the band into which the generator and technology falls.