R00011RAEN G00014BWEN : Elean Business Park

Return to Table

GeneralMapSummaryLFMWh
RO Period Capacity (kW) Load Factor MWh ROCs
2002/2003 36,850 57.1% 184,184 184,184
2003/2004 36,850 79.5% 257,394 257,394
2004/2005 36,850 73.9% 238,460 238,460
2005/2006 36,850 71.5% 230,900 230,900
2006/2007 40,000 62.5% 218,827 218,827
2007/2008 40,000 60.8% 213,790 213,790
2008/2009 40,000 60.2% 210,961 210,961
2009/2010 40,000 61.8% 216,491 324,720
2010/2011 40,000 54.8% 191,999 302,492
2011/2012 43,353 53.9% 205,172 315,103
2012/2013 43,353 60.4% 229,560 351,817
2013/2014 43,353 61.9% 234,992 357,589
2014/2015 43,353 68.4% 259,658 390,187
2015/2016 43,353 68.2% 259,667 389,791
2016/2017 (7) 43,353 62.4% * 138,887 174,088
Annual Totals to end Oct-16 256,213350,239
Rolling Load Factor64.6 %
Annual Load Factor to end Oct-1667.3 %

Notes:

1. RO period is the 12 months from 1 April to 31 March
2. Capacity is the total installed generating capacity in kW
3. Load Factor is calcuated for the 12 months of the RO period.
4. An asterisk (*) denotes fewer than 12 months of data is available in a given period; the actual number of months of data is in brackets in the first column.
5. The number of ROCs per MWh depends on whether the generator is subsidised under the RO and, from April 2009, the band into which the generator and technology falls.