R00016SESC G00675HYSC : Kinlochleven Hydro Power Station, G

Return to Table

GeneralMapSummaryLFMWh
RO Period Capacity (kW) Load Factor MWh ROCs
2002/2003 19,500 93.7% 159,999 159,999
2003/2004 19,500 95.1% 162,847 162,847
2004/2005 19,500 94.8% 161,873 161,873
2005/2006 19,500 95.8% 163,713 163,713
2006/2007 19,500 94.9% 162,107 162,107
2007/2008 19,500 95.5% 163,621 163,621
2008/2009 19,500 93.8% 160,180 160,180
2009/2010 19,500 96.1% 164,085 164,085
2010/2011 19,500 95.3% 162,860 162,860
2011/2012 19,500 93.9% 160,762 160,762
2012/2013 19,500 94.4% 161,239 161,239
2013/2014 19,500 95.9% 163,832 163,832
2014/2015 19,500 96.4% 164,742 164,742
2015/2016 19,500 91.1% 155,976 155,976
2016/2017 (8) 19,500 72.3% * 82,540 43,532
Annual Totals to end Nov-16 137,85898,850
Rolling Load Factor94.3 %
Annual Load Factor to end Nov-1680.5 %

Notes:

1. RO period is the 12 months from 1 April to 31 March
2. Capacity is the total installed generating capacity in kW
3. Load Factor is calcuated for the 12 months of the RO period.
4. An asterisk (*) denotes fewer than 12 months of data is available in a given period; the actual number of months of data is in brackets in the first column.
5. The number of ROCs per MWh depends on whether the generator is subsidised under the RO and, from April 2009, the band into which the generator and technology falls.