R00111SQSC G00424NWSC : Causeymire Wind Farm

Return to Table

GeneralMapSummaryLFMWh
RO Period Capacity (kW) Load Factor MWh ROCs
2004/2005 48,300 26.6% 112,404 103,861
2005/2006 48,300 29.6% 125,093 125,093
2006/2007 48,300 30.6% 129,399 129,399
2007/2008 48,300 29.1% 123,264 123,264
2008/2009 48,300 28.3% 119,643 119,643
2009/2010 48,300 22.5% 95,387 95,387
2010/2011 48,300 25.0% 105,630 105,630
2011/2012 48,300 27.8% 118,097 118,097
2012/2013 48,300 23.3% 98,715 98,715
2013/2014 48,300 30.4% 128,416 128,416
2014/2015 48,300 24.4% 103,407 103,407
2015/2016 48,300 24.8% 105,370 105,370
2016/2017 (6) 48,300 16.8% * 35,875 27,954
Annual Totals to end Oct-16 90,51682,595
Rolling Load Factor26.9 %
Annual Load Factor to end Oct-1621.3 %

Notes:

1. RO period is the 12 months from 1 April to 31 March
2. Capacity is the total installed generating capacity in kW
3. Load Factor is calcuated for the 12 months of the RO period.
4. An asterisk (*) denotes fewer than 12 months of data is available in a given period; the actual number of months of data is in brackets in the first column.
5. The number of ROCs per MWh depends on whether the generator is subsidised under the RO and, from April 2009, the band into which the generator and technology falls.