R00236RQEN G01854NWEN : Fullabrook Wind Farm

Return to Table

GeneralMapSummaryLFMWh
RO Period Capacity (kW) Load Factor MWh ROCs
2011/2012 (9) 66,000 24.3% * 105,643 105,643
2012/2013 (11) 66,000 24.4% * 129,518 129,518
2013/2014 66,000 27.5% 158,734 158,734
2014/2015 66,000 23.0% 132,847 132,847
2015/2016 66,000 26.2% 151,615 151,615
2016/2017 (6) 66,000 16.9% * 48,877 48,877
Annual Totals to end Sep-16 147,067147,067
Rolling Load Factor24.6 %
Annual Load Factor to end Sep-1625.4 %

Notes:

1. RO period is the 12 months from 1 April to 31 March
2. Capacity is the total installed generating capacity in kW
3. Load Factor is calcuated for the 12 months of the RO period.
4. An asterisk (*) denotes fewer than 12 months of data is available in a given period; the actual number of months of data is in brackets in the first column.
5. The number of ROCs per MWh depends on whether the generator is subsidised under the RO and, from April 2009, the band into which the generator and technology falls.