R00199RQWA G01418NWWA : Pant y Wal Wind Farm

Return to Table

GeneralMapSummaryLFMWh
RO Period Capacity (kW) Load Factor MWh ROCs
2012/2013 (2) 46,296 1.9% * 1,218 1,218
2013/2014 46,296 28.9% 117,124 117,124
2014/2015 46,296 29.6% 119,946 119,946
2015/2016 46,296 36.1% 146,994 146,994
2016/2017 46,296 27.7% 112,490 112,490
2017/2018 46,296 31.5% 127,655 127,655
2018/2019 (7) 46,296 19.4% * 46,232 28,833
Annual Totals to end Oct-18 114,61997,220
Rolling Load Factor30.8 %
Annual Load Factor to end Oct-1828.3 %

Notes:

1. RO period is the 12 months from 1 April to 31 March
2. Capacity is the total installed generating capacity in kW
3. Load Factor is calcuated for the 12 months of the RO period.
4. An asterisk (*) denotes fewer than 12 months of data is available in a given period; the actual number of months of data is in brackets in the first column.
5. The number of ROCs per MWh depends on whether the generator is subsidised under the RO and, from April 2009, the band into which the generator and technology falls.